The Hard Labor Creek Reservoir management board and the Walton County Water and Sewage Authority held a join meeting last week to hear updates on the ongoing work on the water treatment facility going up at the site.
Russell Sloss, with Archer-Western Construction, spoke with the board, giving them a look at continuing work and assuring the board members the project remains on schedule to meet a projected open date of January 2028
‘Things are progressing nicely,” Sloss said. “Construction is about 30% complete.”
The next phase of the project will include the need to install pipes and lines across Social Circle Fairplay Road, which will mean some interruptions to traffic on the road for the next few weeks.
“We are doing a road crossing on Social Circle Fairplay Road,” Sloss said. “We hope to start Jan. 12 and we have about three weeks scheduled.”
Sloss said the road will divert traffic onto a temporary route to ensure local travelers can still reach their homes and other destinations on the oft-frequented roadway.
“We’re coordinating with Walton County to build a temporary road and to maintain traffic flow,” Sloss said. “We’ll be doing a road detour there. It will be an additional traffic lane and we’ll have a flagger on site to direct traffic during the day. At night, we’ll have plates set up to allow traffic to travel on the road after hours.”
Sloss said they are doing a great deal of digging work as they lay more pipes on the southern end of the project, too.
“We are running a lot of piping,” Sloss said. “You can’t tell much from an aerial view, but there’s a lot of new pipes buried under the work site now.”
They’re also preparing to connect more of their work to the underwater infrastructure already in place.
“We sent a team of divers into the reservoir to ensure everything is clear,” Sloss said. “Everything looks good, which is promising.”
The board also looked at the next few phases of the water transmission system, which are set to begin construction this year.
Phase 1, which is set to connect the main site to Highway 11, was recently bid out, with the board receiving 10 bids on the project.
Although budget estimates projected a cost of about $19 million, the board is set to go with the low bid of $9.7 million from Mid-South Builders.
Board members questioned whether the lower than expected bids were a concern, but were told the current business climate for construction had many projects coming with lower bids as firms scramble to find work as building projects dry up.
Phase 1 is projected to begin construction by late February.
Two more phases are set to start this year, connecting Highway 11 to Monroe-Jersey Road, and then further on to Highway 138, but bidding is not set to start until later this years as the board works to gain the necessary easements from local homeowners on those routes.
The most immediate project going to bid is the Apalachee River intake facility, which will begin to advertise for bids on Jan. 15 with a projected start date of March.
The board also renewed its contract with Nelson Environmental to continue monitoring Hard Labor Creek downstream to ensure it remains in compliance with the U.S. Army Corps of Engineers.
The boards are set to hold their next join meeting on Feb. 24 on the reservoir site itself to provide a tour of the ongoing work to board members.